As we roll into September, we at WestOne are pleased to announce that there has been much progress in the past month, with many of the internal and external elements now in the final stages of fit out. The installation of windows, tiling and internal partitions and ceilings has now been completed in the majority of the building. The fitting of doors and wardrobes is also underway, almost complete from levels 7 to 10, with the apartments really taking shape.
Meanwhile, air-conditioning and electrical installation has been completed in over 50% of all areas, with testing commencing this week. The lifts have also been successfully tested and certified, ahead of schedule. Finally, the swimming pool structure has now been completed, and is ready for tiling.
We are delighted to report that there have been no delays or accidents, and the project is continuing  well on target!