West One is in the detailed stages of internal fit out. The contractor is working from the top down and upper floors are nearing completion with all internal walls in place, floors and walls tiled, doors being fitted and the electrical and mechanical installations being tested. The lift installations are progressing well and we aim to formally test and certify before the end of July.
Externally, the final façade colour is complete down to level 8. Windows are being installed, and in the coming weeks, the terrace balustrades will be fitted and the scaffold can be removed starting from the top.
Meanwhile, the swimming pool is being concreted. All service ducts are being completed and in a few weeks the contractor will begin preparing the external paving. Keep an eye out for all these exciting developments if you walk down Europort Road this summer!