We are very pleased to report that WestOne is actively coming together. Having topped out, the internal and external blockwork walls throughout the building are now complete. Moreover, works on the roof and the Penthouse have also begun, with all the necessary metal structures in place.
Whats more, inside WestOne is very quickly taking shape. Our technical apartment for purposes of quality control has come together commendably. The studio apartment, assembled by our contractors, demonstrated very high finishes even at this point in time, with the pull down bed and studio kitchen working incredibly well with the design.
Finally, the excavation for the pool and underground plant room will commence next week. We are delighted to report that there have been no delays or accidents, and the project is continuing well on target!