Piling is now finished, and our contractor is nearing completion of the next stage, the welding and concreting of the pile caps. We anticipate this work to be complete next week.

The next stage will be to pour concrete for the ground floor slab and to start the vertical columns for the first floor – keep an eye out for W1 as it starts to rise from the ground!