Now piling is complete our contractor’s efforts are to prepare the foundations! This involves welding the steel cages to the top of the piles and then encasing them in concrete. This work is scheduled to be complete before the end of May and the ground floor slab will be following on behind this work. We anticipate that the ground floor slab will be complete at the beginning of June.

If you happen to be walking by – keep your eyes peeled as we will hopefully begin to watch WestOne rise from the ground throughout summer, reaching its full height in late September.