Since our last update our contractors have made great progress – 300 out of 340 piles are now in place and the pile caps and associated foundations are advancing according to programme. The tie in to the fresh and salt water supply is complete and approved by the utility provider, and the design definition is almost complete and ready for final Client approval within the coming weeks.

Keep your eyes peeled – during the next month we should see the below ground works finished and the structure beginning to rise out of the ground! Whats more, the next major milestone is in sight – the contractor is confident he will be able to complete the structure by the end of September, finishing the “topping out” stage of development.

Overall WestOne Completion Rate: 9%!